2027 ORDER PLANNING

When Should You Place Your Order Before Chinese New Year 2027?

Chinese New Year 2027 falls on February 6. Our factory closes from January 28 to February 15 and reopens on February 16. For goods ready before the closure, your 30% deposit should reach us by December 11, 2026 for orders above 5,000 pcs, or December 16, 2026 for 1,000–5,000 pcs.

LONGRICH POWER manufactures power products in Dongguan, China.

By Jayden Liang, Sales Manager, LONGRICH POWER

Order Deadlines by Quantity

These planning dates apply to existing LONGRICH models when the deposit is received and the artwork and samples are approved.

Goods-ready plan before the factory closure
Order sizeMass productionDeposit received byGoods ready by
1,000–5,000 pcsabout 35 daysDecember 16, 2026January 20, 2027
above 5,000 pcsabout 40 daysDecember 11, 2026January 20, 2027

Dates apply to existing models and assume artwork and samples are already approved.

What Needs More Time

New tooling, custom packaging and certification work add time, which we schedule in the quote.

Stock samples of existing models ship in 3 days. Custom packaging needs a separate sample, so approve the samples before the deposit dates in the table. Discuss the scope through our OEM and ODM process before committing to the schedule.

Booking Your Shipment

We deliver the marked cartons to your designated forwarder in China (FOB). Confirm the last pre-closure shipping date directly with your forwarder and include that date in your project brief.

If You Miss the Deadline

Orders whose deposit reaches us after the applicable date will be scheduled for production after February 16, 2027. We will set the specific production date in the quote.

Plan Your Order

Send the selected model, quantity per model, approved artwork and sample status when you request a quote. The RFQ template guide helps organize the information before you send it.

Buyer FAQ

When is Chinese New Year 2027?

Chinese New Year 2027 falls on February 6.

When does the LONGRICH factory close for Chinese New Year 2027?

Our factory closes from January 28 to February 15, 2027 and reopens on February 16, 2027.

What is the last date to order before the holiday?

For existing models with goods ready by January 20, 2027, the 30% deposit should reach us by December 16, 2026 for 1,000–5,000 pcs, or December 11, 2026 for orders above 5,000 pcs. Artwork and samples must already be approved.

How long does mass production take?

Mass production takes about 35 days for 1,000–5,000 pcs and about 40 days above 5,000 pcs. New tooling, custom packaging and certification work add time, which we schedule in the quote.